top of page
WhiteMenuLogo.png
GET A FREE QUOTE

Rundlepark

Client

Cielle Properties

Size

97,000 sq. ft.

Location

Canmore, AB

Architect

Metafor

Structural Engineer

MMP

General Contractor

Bird Construction

Overview

Rundlepark is a five-storey Nordic spa apartment complex in Canmore with a high level of structural complexity and specification.

Range delivered a full turnkey framing package and was later brought into the design-assist team to help resolve the upper levels, modeling and coordinating the structure to ensure accurate fitment across all systems.

Range Scope

Range provided a turnkey framing package including:

  • Framing labour

  • Prefabricated wall systems

  • All framing materials

  • Roof and floor systems

  • Simpson hardware package

  • Prefabricated stairs

  • Wood frame engineering

  • BIM modeling and design

  • Hoisting operations (including a self-erecting tower crane)

What Made This Project Unique

The project included complex structural conditions such as vaulted ceilings and open-to-below areas, with extensive coordination required between wood, steel, and timber systems.

Range’s involvement in design allowed the team to model Levels 4 and 5 and provide dimensions used by steel and timber suppliers to ensure proper alignment.

Challenges
  • Limited access and multiple hoisting methods required

  • Working in Canmore with constraints on crew size and duration

  • High level of structural complexity

  • Coordination between wood, steel, and timber systems

  • Strict safety expectations from Bird Construction

How Range Delivered

Range worked closely with the architect and structural engineer during pre-design and problem-solving phases. Once the design was finalized, steel and timber suppliers used Range’s dimensions for fabrication.

The team used a Hilti Total Station to lay out each level and maintain consistency throughout the build. Truss design could also be adjusted based on site conditions due to direct access to design information.

Multiple hoisting methods were planned and deployed throughout the project, including rotating telehandlers, a self-erecting T85 tower crane, and additional lifts as needed.

Prefabrication was used to prepare and deliver materials such as blocking, joist components, outlooks, and safety railing systems.

Safety coordination was managed in collaboration with Bow Valley Safety, ensuring proper planning before each phase of work.

results

Schedule: 53,550 man-hours & 864 design and BIM modeling hours

Budget: Fixed price for material supply and install

Risk Reduction: 0 days lost due to material mismanagement

Safety: Zero safety infractions

Range Construciton LTD. - Background Texture Image

other
projects

VIEW PROJECTS
bottom of page